Field Projects

Heavy civil work across the Western U.S.

Documented fieldwork on remote roads, trails, bridges, and water infrastructure across the Western U.S., executed under federal and public-sector standards.

Completed ADA-accessible paved trail through the Freeman Giant Sequoia Grove, Sequoia National Forest

Completed Project

Bush Loop Accessible Paved Trail Reconstruction

Sequoia National Forest, CA  ·  USDA Forest Service  ·  Completed

CA Mathes Construction rebuilt 0.46 miles of ADA-accessible paved trail through the Freeman Giant Sequoia Grove in Sequoia National Forest. Our crews replaced seven corrugated metal pipe (CMP) culverts, placed new asphalt paving, built an asphalt berm along the trail edges, and finished the surface with a protective seal coat.

Working in a grove of old-growth giant sequoias meant hauling paving and grading equipment up mountain roads, working inside a tight footprint, and protecting the trees, soil, and drainage at every step. The result is a smooth, accessible trail that visitors of all abilities can use to experience the grove.

Scope of work

  • Replacement of seven CMP culverts
  • ADA-accessible asphalt trail paving
  • Asphalt berm construction
  • Seal coat application
  • Mobilization to a remote mountain site with limited access

Current Project

Work underway

Pine Canyon Barracks Replacement

Los Padres National Forest, CA  ·  USDA Forest Service  ·  Under construction

At the Pine Canyon Fire Station along the Cuyama River, CA Mathes is removing the station’s existing mobile-home barracks and replacing it with a new wildland-urban interface (WUI) fire-rated, four-bedroom barracks unit. Our crew is handling demolition and disposal, regrading and compacting the pad, setting the new unit on piers with seismic tie-downs, and reconnecting power, water, and sewer, all while keeping the fire station in service and the river corridor protected.

Bids Submitted

Projects we are pursuing

San Bernardino Road Grading & Drainage

San Bernardino National Forest, CA  ·  USDA Forest Service  ·  Bid submitted

Road and drainage maintenance on fifteen native-surface roads across several ranger districts: nearly 61 miles of blading, re-establishing rolling dips and lead-off ditches, and installing seven new overside drains. The rocky, steep terrain calls for bulldozer-based grading rather than a standard motor grader.

Sand Pond Trail Boardwalk

Tahoe National Forest, CA  ·  USDA Forest Service  ·  Bid submitted

Replacement of the accessible boardwalk and a 25-foot trail bridge on the Sand Pond Interpretive Trail, crossing Sardine Creek and an adjoining wet meadow. Our approach carries about 1,060 feet of boardwalk on pinned pier foundations, with no excavation or concrete in the meadow, and sets the new trail bridge on helical piles.

Excavator loaded on a lowboy trailer at dusk in the Sierra Nevada

Field Standards

Quality, logistics, and environmental discipline

Remote and protected wilderness sites demand disciplined planning. Our crews manage materials, access, and equipment deployment with safety, quality, integrity, and efficiency as the basis for every task order.

Environmental containment, NEPA-aligned review, and engineering precision guide work in sensitive areas, supporting federal agencies and public partners from design through closeout.